Cushaling Wind Farm

  1. Home
  2. Cushaling Wind Farm

Using our expert crane services to contribute to the development of Ireland’s renewable energy infrastructure

Key facts

The Cushaling Wind Farm is a 55MW onshore wind farm in Ireland that consists of 9 turbines.

Client: Statkraft Ireland Ltd
Other key stakeholders: Vestas Ireland (Project Supervisor Construction Stage), Natural Power Consultants Ltd (Project Supervisor Design Process)
Project type: Installation and Maintenance
Product installed: Vestas V162 6.2MW EnVentus wind turbine generators
(WTGs)
Highlights: Delays minimised by adhering to project timelines
Project length: 7 months
Cranes used: LTM1500, LTM1230, LG1750

Cushaling wind farm 1
Cushaling wind farm 2

Project Scope

This project involved the installation of nine Vestas V162 6.2MW EnVentus wind turbine generators (WTGs), a significant undertaking that demanded meticulous planning and expert execution. AIS Wind Energy was awarded the contract to provide comprehensive crane services for both the pre-installation and main installation phases of the Cushaling Wind Farm project. This included the mobilisation, operation, and demobilisation of cranes for both the pre-assembly and main assembly stages. Specifically:

  • Pre-assembly: Utilising an LTM1500 and LTM1230 crane, the pre-assembly phase took place between July 12th and July 27th, 2024 (WW28)
  • Main assembly: Employing an LG1750 and LTM1230 crane, the main assembly phase occurred from August 10th to December 12th, 2024 (WW32)

We managed the logistics of lifting and positioning the turbine components, working in close collaboration with Vestas Ireland. Subcontractors Gabriel O’Brien Crane Hire Ltd, O’Grady Crane Hire, and AMS Lifting Services Ltd were hired to support the crane operations.

Challenges

  • Logistical complexity: The sheer size and weight of the V162 6.2MW EnVentus WTG components posed significant logistical challenges. We addressed this by implementing detailed lift plans and utilising high-capacity cranes capable of handling these loads.
  • Time constraints: Adhering to the project timeline – with component deliveries starting on May 20th, 2024, and the main assembly finishing on December 12th, 2024 – required efficient project management. We ensured timely crane mobilisation and maintained a strict schedule.
  • Site conditions: Wind farm construction sites can present challenging terrain and weather conditions. Our experienced team adapted to these conditions, ensuring safe and efficient crane operations.
Cushaling wind farm 3
Cushaling wind farm 5

Outcome

Thanks to our team of skilled operators and project managers, the project was completed to the high standards expected by Statkraft and Vestas. Our previous expertise in wind turbine installation was crucial in ensuring crane operations were successfully and safely executed for both the pre-assembly and main assembly phases, adhering to the project schedule and ensuring the integrity of the turbine components.